Case Study: PLM Point Count & Composite Analysis Methods

A significant portion of our business comes from insurance and restoration companies specializing in mitigating the effects of flooding and fires. These companies require asbestos testing whenever the damage caused by natural disasters—small or big—necessitates the removal of existing building materials.

In November 2024, Nicole, a Project Manager at Mitigate Pros in Denver, reached out to us for asbestos testing in a condo bathroom that required renovation due to a major pipe leak. Our inspector collected a total of nine samples from the following homogeneous materials:

  • Orange peel texture
  • Drywall with joint compound
  • Vinyl sheet flooring 3 layers
  • Tile, mortar, grout

The samples were tested at Atlas Laboratory in Englewood with a standard preliminary  PLM Bulk method and all 5 drywall samples came out positive for asbestos. See Table 1 below for the details.

Table 1.

Sample Asbestos Content(Suspect) Asbestos Containing Material
NumberLocationHomogeneous MaterialLayerDescriptionPLM BulkPoint CountComposite AnalysisFriabilityConditionQuantity
(sq. ft.)
1-11-21-3Bathroom, Wall B Bathroom, Ceiling Bathroom, Wall DSM- Orange Peel Texture1Paint / Texture2%  ChrysotileFriableSignificantly Damaged300
1Paint / Texture<1% Chrysotile
 
FriableSignificantly Damaged300
1Paint / Texture2%  ChrysotileFriableSignificantly Damaged300
2DrywallNDFriableSignificantly Damaged300
2-12-2Bathroom, Ceiling Bathroom, Wall DMISC- Drywall with Joint Compound1Paint / Joint Compound2% ChrysotileFriableSignificantly Damaged300
2Drywall TapeNDFriableSignificantly Damaged300
3Joint Compound3% ChrysotileFriableSignificantly Damaged300
4DrywallNDFriableSignificantly Damaged300

Based on the results of standard PLM bulk testing, 300 square feet of drywall would have needed to be removed by a professional abatement company under containment to prevent asbestos spill. However, we requested the lab to perform additional composite analysis on the joint compound, and our client agreed to point-count three drywall samples at an additional cost of $185. The results of the two new procedures applied to the asbestos-hot samples were extremely satisfactory. Refer to Table 2 for the results of these additional testing procedures.

Table 2.

Sample Asbestos Content(Suspect) Asbestos Containing Material
NumberLocationHomogeneous MaterialLayerDescriptionPLM BulkPoint CountComposite AnalysisFriabilityConditionQuantity
(sq. ft.)
1-11-21-3Bathroom, Wall B Bathroom, Ceiling Bathroom, Wall DSM- Orange Peel Texture1Paint / Texture2%  Chrysotile0.25%FriableSignificantly Damaged300
1Paint / Texture<1% Chrysotile
 
0.75%FriableSignificantly Damaged300
1Paint / Texture2%  Chrysotile0.75%FriableSignificantly Damaged300
2DrywallNDFriableSignificantly Damaged300
2-12-2Bathroom, Ceiling Bathroom, Wall DMISC- Drywall with Joint Compound1Paint / Joint Compound2% Chrysotile<1%FriableSignificantly Damaged300
2Drywall TapeNDFriableSignificantly Damaged300
3Joint Compound3% Chrysotile<1%FriableSignificantly Damaged300
4DrywallNDFriableSignificantly Damaged300

The composite analysis of the joint compound and the PLM point-count analysis of the drywall revealed that the asbestos content was below the regulatory limit of 1%. As a result, the abatement of any ACM was no longer required for this project. The estimated cost savings from this outcome were approximately $5,000.